Generate Test Execution Weekly Progress Report
Reports can be generated on test execution weekly progress statistics.
Please follow below steps to generate "Test Execution Weekly Progress Report":
- Open a Jira project
- Click "SynapseRT Reports" from the left navigation panel
- From the list, find "Test Execution Weekly Progress Report"
- Click "Test Execution Weekly Progress Report"
- Specify from the filter options below and click the "Generate Report" button:
- Select a JIRA project from "Project" dropdown list
- Select a Test Plan from "Test Plan" dropdown list (optional)
- Select a Test Cycle from "Test Cycle" dropdown list (optional)
- Specify "Executed between"
You can save your selections as an "Report Configuration" to reuse it in the future.
[Screenshot - UG96_Test_Execution_Progress_Report_Configuration]
[Screenshot - UG96_Test_Execution_Progress_Report_Result]